Green Projects
Green Projects showcases Green Infrastructure improvements made in the city of Syracuse.
Please click the links below to view projects. Check back often as new projects are completed and updated on a regular basis.
2012 Projects
Project Title | Type of GI Technology | *Cost | ** Capture (gal/yr) |
Atrium Garage |
Cistern |
$2,875 |
38,400 |
OCPL – Beauchamp Library |
Bioretention/ Rain Garden |
$112,000 |
265,000 |
OCPL – Hazard Library |
Porous Pavement, Bioretention |
$170,000 |
370,000 |
OCPL – Mundy Library |
Porous Pavement, Tree Trench
|
$188,000 |
215,000 |
OCPL – Petit Library |
Porous Pavement,
|
$130,000 |
254,000 |
OCPL – White Library |
Porous Pavement, Rain Garden, Rain Barrel, Infiltration Trench |
$180,000 |
424,000 |
Rain Barrel Program 2012 |
Rain Barrels |
TBD |
TBD |
Street Tree Contract 2012 |
Street Tree Plantings |
TBD |
2,000,000 |
Westcott Community Center |
Porous Pavers, Rain Barrel |
$52,500 |
153,000 |
2011 Projects – Ongoing
Project Title | Type of GI Technology | *Cost | **Capture (gal/yr) |
Avery Ave – Park Greening at
|
Rain Garden |
$316,420 |
746,000 |
Connective Corridor – Forman Park |
Landscape Enhancement |
$50,000 |
121,000 |
Connective Corridor -Phase 1,
|
Green Street |
TBD |
2,494,366 |
Delaware Rain Garden
|
Rain Garden |
$0 |
TBD |
Greening the Gray at Basin 044 |
Downspout Disconnection |
$0 |
69,000 |
Greening the Gray at Basin 045 |
Downspout Disconnection |
$0 |
69,000 |
Greening the Gray at Clinton
|
Bioretention, Green Separation |
$0 |
5,152,000 |
Greening the Gray at Harbor
|
Bioretention, Porous Pavement |
$0 |
305,000 |
OnCenter Municipal Garage |
Bioretention |
$246,985 |
1,277,000 |
Otisco Street Green Corridor (Phase 1) |
Green Street |
$1,413,732 |
2,240,845 |
Pocket Park at W. Genesee & N. Clinton
|
Porous Pavement, Bioretention |
$105,000 |
125,000 |
SCSD Central Offices Parking Lot |
Infiltration Beds |
$403,500 |
2,036,619 |
SCSD Hughes Magnet School |
Porous Pavement |
$288,000 |
1,504,000 |
SCSD Institute of Technology |
Separation |
$0 |
2,251,000 |
SCSD Dr. Weeks Elementary |
Bioretention |
$89,000 |
2,177,000 |
Skiddy Park Enhancements |
Porous Pavement |
$244,000 |
898,000 |
Sunnycrest Park – Golf Course
|
Bioretention |
$362,599 |
843,000 |
SUNY Upstate Green Roof |
Green Roof |
$0 |
211,000 |
SUNY Upstate Rain Garden/Trees |
Rain Garden/Trees |
$0 |
65,000 |
SUNY Upstate – Institute for
|
Tree Trench |
$0 |
18,000 |
Vacant Lot Project: 701 Oswego Street |
Infiltration Trenches, Urban Garden |
$85,214 |
259,000 |
Wilbur Ave Zoo Entrance |
Rain Garden |
$299,990 |
680,000 |
2011 Projects – Completed
Barnabas Center – Onondaga Earth
|
Rain Gardens, Green Wall |
$0 |
38,875 |
Bellevue Academy |
Tree Plantings |
$0 |
20,000 |
Bishop Foery – Onondaga Earth
|
Rain Gardens, Rain Barrels |
$0 |
29,303 |
CNY Jazz Arts Foundation – GIF |
Green Roof |
$52,188 |
53,000 |
CNY Philanthropy Center – GIF |
Green Roof, Bioretention, Porous Pavement |
$62,700 |
88,310 |
Concord Place |
Green Street |
$78,900 |
955,000 |
Connective Corridor – Phase 1, Contract 1 |
Green Street |
$948,717 |
5,742,000 |
County Board of Elections Bldg |
Bioretention (Stormwater Planter) |
$0 |
114,000 |
Downtown Streetscapes –
|
Enhanced Street Trees |
$133,400 |
131,000 |
Downtown Streetscapes –
|
Enhanced Street Trees |
$96,600 |
169,000 |
Elephant Exhibit – Rosamond Gifford Zoo |
Green Roof |
$183,900 |
114,000 |
Erie Canal Museum Green Roof |
Green Roof |
$73,480 |
39,000 |
Galleries Office Towers – GIF |
Underground Infiltration |
$100,000 |
352,000 |
Geddes St Road Reconstruction |
Bioretention |
$203,000 |
523,000 |
Harbor Brook Wetland –
|
Treatment Wetland |
$260,000 |
0 |
Harrison Street –
|
Green Street |
$109,920 |
180,000 |
Hazard Library Green Roof |
Green Roof |
$67,275 |
88,000 |
Hotel Skyler – GIF |
Porous Pavement, Cistern |
$100,000 |
173,000 |
Matawon Development Group – GIF |
Infiltration Trench |
$24,214 |
73,600 |
Monroe Building – GIF |
Green Roof |
$99,311 |
91,581 |
OnCenter Green Roof |
Green Roof |
$1,038,000 |
1,033,000 |
OnCenter Surface Lot |
Porous Pavement, Tree Trench |
$529,040 |
2,360,000 |
Putnam Properties – GIF |
Green Roof |
$75,757 |
81,000 |
Rain Barrel Program 2011 |
Rain Barrels |
$35,937 |
1,216,413 |
Skiddy Park: Courts4Kids – GIF |
Porous Pavement |
$164,674 |
344,400 |
Spa at 500 W. Onondaga – GIF |
Bioretention |
$60,000 |
150,000 |
Street Tree Contract A |
Enhanced Street Trees |
$1,222,352 |
814,000 |
Street Tree Contract B |
Enhanced Street Trees |
||
Sunnycrest Arena Parking Lot |
Porous Pavement |
$407,000 |
1,876,000 |
Townsend Median Phase 1 |
Bioretention |
$86,000 |
317,000 |
Townsend Median Phase 2 |
Bioretention |
$43,000 |
53,000 |
Tree Plantings in Court Woodlawn |
Community Tree Planting |
$0 |
118,000 |
Tree Plantings in Schiller Park |
Community Tree Planting |
$0 |
160,000 |
Tree Plantings in Union/Demong Parks |
Community Tree Planting |
$0 |
48,000 |
Vibrant Syracuse Spaces – GIF |
Porous Pavement, Bioretention |
$153,618 |
440,000 |
War Memorial Cistern System (Phase 1) |
Stormwater Reuse Cistern |
$1,229,251 |
400,000 |
Water Street Gateway |
Infiltration Trench & Porous Pavers |
$920,088 |
924,000 |
Water Street Pavement Removal |
Pavement Removal |
$124,000 |
768,000 |
2011 ESTIMATED TOTAL :
|
|
$12,586,762 |
43,619,312 |
2010 Projects – Completed
City Parking Lot #3 |
Porous Pavement, Bioretention |
$239,102 |
678,000 |
City Parking Lot #21 |
Bioretention, Infiltration Trench |
$188,046 |
462,000 |
Creekwalk: Jefferson to Walton |
Porous Pavement, Bioretention |
$63,000 |
135,000 |
Creekwalk: Walton to Fayette |
Porous Pavement |
$47,000 |
119,000 |
Dunbar Association – GIF |
Porous Pavement |
$100,000 |
225,000 |
Grand Ave Sidewalk |
Porous Pavement |
$100,000 |
10,000 |
Jefferson Clinton Commons – GIF |
Green Roof, Porous Pavement |
$100,000 |
299,000 |
King + King Architects – GIF |
Green Roof |
$100,000 |
197,000 |
NWSI Artist Studio/Apartment – GIF |
Porous Pavement, Rain Garden,
|
$22,769 |
130,000 |
NWSI Lincoln Building – GIF |
Bioretention, Tree Planters,
|
$78,000 |
476,000 |
Pearl Street Parking Lot |
Porous Pavement |
$397,000 |
1,286,000 |
Primate Exhibit – Rosamond Gifford Zoo |
Cisterns, Porous Pavement, Rain Garden |
$25,000 |
613,000 |
St. Lucy’s Church – GIF |
Porous Pavement |
$125,000 |
246,000 |
SUNY-ESF Residence Hall – GIF |
Bioswales, Cisterns,
|
$78,000 |
62,000 |
Syracuse Model Neighborhood – GIF |
Rain Gardens |
$250,000 |
387,000 |
Townsend Street Parking Lot |
Infiltration Trench |
$342,000 |
975,000 |
Tree Enhancement in Burnet Park |
Tree Plantings |
$11,480 |
82,000 |
2010 TOTAL: |
|
$2,266,397 |
6,382,000 |
2011 TOTAL: |
|
$12,586,762 |
43,619,312
|
COMBINED TOTAL (2010-2011): |
|
$14,853,159 |
50,001,312 |