Green Streets in CSO 060/077 Sewershed


Project Description: The Green Streets in CSO 060/077 Sewershed projects are comprehensive green street applications located on multiple streets within the CSO 060/077 sewershed. This is a high priority sewershed that discharges frequently during rain events. The green streets are listed below and include capture area and runoff reduction estimates:

  • Elk St. (Anticipated Summer 2020)
    Capture Area: 51,784 sq. ft.
    Runoff Reduction: 1,000,000 gal/yr
    Anticipated Project Cost: $422,300
  • Moore Ave. (Anticipated Summer 2020)
    Capture Area: 57,490 sq. ft.
    Runoff Reduction: 1,110,000 gal/yr
    Anticipated Project Cost: $810,000
  • Robert Dr. (Anticipated Summer 2020)
    Capture Area: 72,727 sq. ft.
    Runoff Reduction: 1,400,000 gal/yr
    Anticipated Project Cost: $470,000
  • Vincent St. (Anticipated Summer 2020)
    Capture Area: 106,000 sq. ft.
    Runoff Reduction: 2,050,000 gal/yr
    Anticipated Project Cost: $1,210,000
  • Colvin St. and Warner Ave  (Anticipated Summer 2020)
    Capture Area: 150,000 sq. ft.
    Runoff Reduction: 2,450,000 gal/yr
    Anticipated Project Cost: $1,525,000

Each design implements green infrastructure applications at key points along these streets in order to capture stormwater and enhance local urban streetscapes. Each project also incorporates the installation of infiltration trenches underneath the roadway, tree planters, and bioswales throughout the project areas.


Download project details below:

Previous post:

Next Project:

Project Details

$4,497,600
Total Amount
Cost
8,021,000
Gallons Per Year
Capture