The Stadium Lot at SU was constructed in 2011 by Syracuse University. The project consisted of the installation of a porous concrete and infiltration bed system along the edges of the parking lot to capture runoff from the parking lot. In addition, a slow release system is included in the design to allow for the stormwater to slowly release into the combined sewer when it reaches a certain elevations. In total, this project captures approximately 2,131,000 gallons annually.
Stadium Parking Lot
Status: Completed
GI Technology: Bioswale
Project Year: Archived
NO COST
*TOTAL cost
2,131,000
**TOTAL CAPTURE: GAL/YR