Factory Direct Furniture And Mattress

Status: Completed
GI Technology: Green Roofs
Project Year: 2019

287400

*TOTAL cost

863100

**TOTAL CAPTURE: GAL/YR

 

Project Description:

The Factory Direct Furniture and Mattress project, located at 2711 South Salina
Street and was completed in the Fall of 2019. The project replaces the currently impervious asphalt
parking lot with porous pavement and adds greenspace, each managing stormwater from the parking
lot and the furniture store building roof. Approximately 29,000 square feet of porous asphalt and 2,000
square feet of added greenspace were installed. Two roof drains on the building were disconnected from
the combined sewer and retrofitted to discharge to the porous asphalt. Overall, the installed green
infrastructure captures approximately 863,100 gallons of stormwater runoff annually.